Evaluating Alternatives to Meet Deployment Timeframes for a New Claims Management System


How do you staff a training project with almost 1,700 users in 31 locations that will require approximately 2,300 manhours of time and the business unit wants it done in two months? Adding to the complexity, the 1,700 users were in over 50 different job titles. The 10 modules of the new system had to be mapped into curriculum for every job title to provide them with the training they needed.
The document to the right is the analysis of alternative ways of resourcing the project to meet schedule demands. Click the document image to open it.
There are also links to the Key Results Summary for this project and a link to a page with more project documents / samples. There are also two infographics. One for the project demographics and another depicting the schedule / resourcing options.
key results
Read the Key Results Summary for this Project
project documents work samples
See More Project Documents / Work Samples for this Project
Schedule / Resourcing Analysis & Recommendation Report
 schedule resource analysis recommentation

Project Demographics and Metrics Infographic
project demographics metrics infographic
Project Schedule / Resourcing Alternatives Infographic
project schedule resource alternatives infographic